May 8, 2006, St Petersburg, Florida:

The first truckload of fill arrives after a delay of two hours due to the first rain St. Petersburg has had in months.
The project will eventually require over 300 cubic yards of fill and topsoil. Each truckload is 20 cubic yards of earth. At the end of the day four of the mounds had been completed.

May 9, 2006, St Petersburg, Florida:

The earth movement continued. By the end of the day more than seven mounds had been completed and were ready for the last
six inches of topsoil. All of the mounds will be covered with sod. Sherry estimates it will require 8500 sq. feet of sod to compete the project.