INSTALLATION FEBRUARY 7TH, 2005!........................ pg. 1 of 2

February 7, 2005; At CW Elaborations, INC. in Denver, Colorado:

The painting of the heads was completed and they were ready to transport the heads to City Park.
At 8:00AM they were rolled out of the paint shop and lifted by crane onto the flatbed semi for the trip.

February 7, 2005; In City Park, Denver, Colorado:

Arrival at the site. The crane was set up and the heads gently lifted off the truck and swung onto the ground next to the base.
The female head was the first to be set into place. The bolts were perfectly aligned and the base plates slipped on with no trouble. Mike, from Juno, said it was his easiest installation ever.

February 7, 2005; In City Park, Denver, Colorado:

The nuts were attached and tightened up. The male head was not quite as easy. A few of the bolts were just slightly off and so the crowbars and hammers came out of the truck.
We rocked the head back and forth and with a little manhandleing and about 30 minutes it slid into place. All that was left was to tighten the bolts. A few days later the concrete was poured into the squares and the piece was finished. See the next page >>.